How to use a gantt chart in RTC?
We have an RTC project area based on formal project management template.
I want to know how to use MPP like gantt chart capability in RTC. I know there is a work breakdown view in RTC plan but want to know what are the factors that construct that view, i.e what are the fields that need to be selected in Plan item and its child tasks, how does a work item state contributes to it and what kind of links has to be setup between tasks to create dependencies. Any help is much appreciated. |
Accepted answer
Ralph Schoon (63.3k●3●36●46)
| answered Nov 17 '16, 3:45 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Some hints:
Rohit Rishabh selected this answer as the correct answer
Comments Thanks Ralph, it helped.
Ralph Schoon
commented Nov 17 '16, 12:53 p.m.
| edited Nov 17 '16, 12:53 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Sometimes my FF gets totally confused and I can not login to Jazz.net and all kind of problems. Then I have to delete the complete history. This helped in the past.....
Geoffrey Clemm
commented Nov 17 '16, 1:43 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
I have also found that Chrome worked better. My version of Firefox has just upgraded itself, so we'll see if that makes the problem better or worse (:-).
|