How to change default Work Item type for Implemented By Link?
Hello,
I'm trying to customize Formal Project Management RTC template. As a part of the customization I want to change default work item type for Implemented By link from Change Request work item type to Task work item type. How could I achieve this goal? -Thanks in advance |
One answer
I've found the answer:
I need to open Project Area Template and change Change Management Type Binding for Implementation Request from Change Request to Task |