How can I query out what work items are included in a Build through RTC client?
Zhou Xing (41●1●2●3)
| asked Jul 09 '12, 7:58 p.m.
JAZZ DEVELOPER edited Jul 10 '12, 12:16 a.m. by David Olsen (523●7)
I'm using RTC plain Java client, is there a way to query out what work items are included in a Build? thanks
|
2 answers
If you open the Build, the included work items will appear under the Contribution Summary heading in the Overview tab. You can also open and view work items against the given build by using the Reported Work Items heading in the Overview tab.
Comments
Brian DiCola
commented Nov 21 '13, 1:38 p.m.
Is there a reference or article that explains the details of how RTC figures out what work items go into a build? Thanks.
sam detweiler
commented Nov 21 '13, 2:39 p.m.
when u check in a change (set), you are prompted for the workitem causing you to do this work.
1
Got this from the Build team:"The "Included in build" links are generated during the SCM accept phase of the build (whether done by JBE or the teamAccept Ant task), for any work items associated with change sets accepted into the build workspace."
Brian DiCola
commented Nov 21 '13, 7:34 p.m.
|
I only found the internal, com.ibm.team.build.internal.client.workitem.WorkItemHelper.
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.