It's all about the answers!

Ask a question

[bug] Problem setting work item estimated time in min/sec


Michael Leithner (1131910) | asked Oct 12 '11, 8:25 a.m.
If i set the attribute "estimated time" (Schtzung) not to hours but minutes or seconds
it is automatically set to a huge number if reload the item again (e.g. 2562047788015,22 or something about that).

This also kills my plan / product backlog -> estimated time


How can i
a) prevent this error? or
b) prevent the user using other format than hours?



PS: is it possible to post some screens for further explaination here in the forum?

2 answers



permanent link
Ralph Schoon (63.4k33646) | answered Oct 12 '11, 11:22 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
I have briefly looked into the work items and there are some asking for enhancements i haven't found you case. I think you should consider to create a work item for this behavior.

permanent link
Michael Leithner (1131910) | answered Oct 13 '11, 4:41 a.m.
ok, ralph thanks for your reply,
i have created a workitem:
https://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=com.ibm.team.workitem.viewWorkItem&id=180389&tab=overview

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.